South Africa’s nuclear build faces its hardest question; the price
As Eskom submits its feasibility study for 5,200 MW of new nuclear power, a leading energy scholar asks what the government has not yet said: what it will cost, whether the modelling justifies it, and who will pay.
Key points
- South Africa plans 5,200 MW of new nuclear capacity by 2039 under its Integrated Resource Plan 2025, with the first 1,200 MW due by 2036; and an option to expand to 10,000 MW. 2
- Eskom has submitted its feasibility report for the programme, and Electricity Minister Kgosientsho Ramokgopa intends to publish the procurement determination before June 2027, after public consultation. 5
- Energy scholar Mark Swilling, writing in the Daily Maverick on 24 November, says the government has never presented the cost of the nuclear build; and questions whether the modelling behind it justifies 5,200 MW at all. 1
- Lazard’s latest cost study puts new nuclear power at $175–$255 per megawatt-hour, against $40–$98 for utility-scale solar and $37–$99 for onshore wind; though it excludes the cost of keeping the grid stable. 9
- Recent Western nuclear builds ran far over budget: Vogtle in the US cost $36.8 billion against a $14 billion estimate, and Flamanville in France cost €13.2 billion against €3.3 billion planned. 13
ONE EVENT. THREE READINGS.
How the West reads it: a financing problem dressed as an energy debate.
The Western reading treats South Africa’s nuclear question as a problem of money and delivery, not of physics.
What this reading highlights: Lazard’s tables, the Financial Times on Hinkley Point C and the French Court of Auditors on Flamanville tell the same story: the West knows how to build reactors, but it has forgotten how to build them on budget.
Any investor would ask the same before committing R250 billion. The West’s own answer is hedged: existing nuclear plants are among the cheapest power to run, at $26–$36 per megawatt-hour, which is why Koeberg’s extension to 2044 and 2045 draws no argument.
Sources: Nuclear Engineering International (1), Lazard (1), Ember (1), Energy Central (1), IAEA (1)
How the East reads it: build fast, build cheap, and let solar set the pace.
The East’s reading is set by the fastest builder.
What this reading highlights: China added 336 terawatt-hours of solar power in 2025, more than every other region in the world put together (Economic Times, on Ember’s data), and India, through Down To Earth, covered the same finding: renewables have overtaken coal for the first time in a century.
From the East, the lesson is speed and manufacturing scale: solar and wind will overtake nuclear in 2026, and the East still builds nuclear at scale, but beside the cheapest solar ever seen. The question is whether Pretoria can build at the East’s pace.
Sources: Down To Earth (1), The Economic Times (1)
How the Global South reads it: sovereignty, tariffs and a grid that cannot keep up.
The Southern reading is the South African one, and it is about who pays and who decides.
What this reading highlights: The Daily Maverick, IOL and Moneyweb frame the same tension: a government arguing for energy sovereignty and industrial growth, against households paying for a grid that cannot absorb the solar power it has.
The grid operator expects to pay R4 billion this year for power from solar and wind farms it orders to switch off. From the South, the nuclear question is inseparable from that bill; and from the R400 billion transmission plan. Egypt is building; Ethiopia has launched its own programme; the continent watches Pretoria.
Sources: Daily Maverick (1), Parliamentary Monitoring Group (1), South African Government (1), IOL (1), Moneyweb (2), St Francis Chronicle (1), CNBC Africa (1)
Sources by lens: 5 West, 2 East, 8 Global South. See every source
THE POINT OF CONVERGENCE
On the plan; South Africa will build 5,200 MW of new nuclear capacity by 2039 under IRP 2025, with the first 1,200 MW due by 2036 and an option to reach 10,000 MW; Eskom has submitted its feasibility study and the minister aims to publish the procurement determination before June 2027.
WHAT REMAINS CONTESTED
On the numbers; new nuclear power is the most expensive new-build generation in Lazard’s latest cost study at $175–$255 per megawatt-hour, against $40–$98 for utility-scale solar and $37–$99 for onshore wind; and the Western record is one of overruns, from Vogtle’s $36.8 billion to Flamanville’s €13.2 billion.
The story
A scholar, a webinar and a question the government has not answered
The challenge to South Africa’s nuclear programme arrived in the morning papers, not in parliament. Mark Swilling, one of the country’s best-known energy scholars, used an op-ed in the Daily Maverick on Tuesday 24 November to ask the question he says the government has never answered in public: what will 5,200 megawatts of new nuclear power actually cost; and does the modelling behind the plan justify building it at all?
The timing was deliberate. Twelve days earlier, on 12 November, energy analyst Chris Yelland hosted a webinar on the business case for new nuclear power, with government, academic and civil-society speakers. Swilling, who gave the opening talk, writes that the three government representatives presented detailed justifications for new nuclear capacity by 2040 but never once referred to the costs, and that Grove Steyn, one of South Africa’s most experienced energy modellers, said the inclusion of nuclear in the Integrated Resource Plan 2025 was not justified by the modelling used to produce it. “This is not evidence-based policymaking,” Swilling writes, “and every potential investor knows this.” The St Francis Chronicle independently confirmed the webinar.
The plan on paper: 5,200 MW, two sites and a R250bn first estimate
The plan itself is not in doubt. The Integrated Resource Plan 2025, approved by cabinet and gazetted in October 2025, provides for 5,200 MW of new nuclear capacity coming online between 2036 and 2039, with an option to expand to 10,000 MW. Eskom has now submitted its feasibility report, and Electricity and Energy Minister Kgosientsho Ramokgopa says his department is preparing a section 34 determination for public participation, which he intends to publish before June 2027.
Koeberg, on the Atlantic coast north of Cape Town, is the only commercial nuclear power station in Africa: two reactors of 920 MW each, in service since the mid-1980s, supplying about 1,860 MW, licensed to 2044 and 2045. Two sites are in play: Duynefontein, beside Koeberg, authorised for at least 2,400 MW, and Thyspunt, where processes are still under way. The early cost figure in public is about R250 billion, roughly $15 billion, for the 5,200 MW programme. See our South Africa factbook.
Lazard’s Levelized Cost of Energy+ study puts a new nuclear plant at $175–$255 per megawatt-hour, against $40–$98 for utility-scale solar and $37–$99 for onshore wind. The Western record points the same way: Vogtle in the United States, approved at $14 billion, finished at about $36.8 billion, seven years late; Flamanville in France, planned at €3.3 billion, cost €13.2 billion (€23.7 billion with interest, per the French Court of Auditors); Hinkley Point C in Britain, announced at £18 billion in 2015, is now expected to cost at least £49 billion if its first unit enters service in 2030. Renewables supplied 33.8% of global electricity in 2025, overtaking coal for the first time in more than a century, with solar alone meeting 75% of demand growth (Ember).
“This is not evidence-based policymaking,” Swilling writes, “and every potential investor knows this.”
What will 5,200 MW actually cost; and who will pay?
The central fact of this story is a missing one: no official total cost has been published. The R250 billion figure is an early estimate, not a budget, and the government has not said what the plants will cost to build, what they will add to tariffs, or how the programme will be financed. Nor has it published the modelling behind the 5,200 MW figure; the point Steyn made at the webinar, and the point Swilling is pressing. Without it, the public cannot test whether the capacity is needed at all.
Almost everything else is undecided: no vendor, no site, no funding model; the terms of the public-private partnership are unknown. The minister has said he expects the process to be challenged in court, and it is not known whether the determination will survive. The timetable is known: a position paper by the end of November, 60 days of comment, a determination before June 2027.
Why this is the biggest energy decision since Kusile
South Africa still gets more than 80% of its electricity from coal, and the choice it makes now will shape tariffs, industry and the climate for forty years. A build on this scale is the largest energy commitment since the Kusile coal station; as the state is already committed to a R2.2 trillion generation plan and a R400 billion grid expansion. If costs run as in the West, households will pay for decades through their bills; if the build is abandoned midway, as V.C. Summer was in the US after $9 billion spent, the loss falls on the same people.
Koeberg is Africa’s only operating nuclear plant; Egypt is building the second. How Pretoria handles the cost question will set the precedent across Africa. Our earlier reporting on the debate at COP31 is here: South Africa’s nuclear push, and the activists who answered it.
Why does the cost argument cut both ways?
Both sides are using the right numbers for the wrong comparison. Lazard’s tables are real, but Lazard itself says its levelised cost excludes the expense of keeping a grid stable: the firming, storage and transmission without which cheap solar cannot reach a socket in the evening. South Africa lives it: rooftop solar has reached 9,107 MW, midday supply exceeds demand, and the operator pays farms for power it cannot use. A reactor’s $175–$255 per megawatt-hour buys firm power, day and night; solar’s $40–$98 buys power only when the sun shines. The true comparison is the cost of the whole system, and neither side has published one.
That is why Swilling’s strongest point is procedural: his case rests on the fact that government representatives presented a case for 5,200 MW without mentioning cost, and that the modelling has not been shown. A government asking the public to trust a R250 billion programme should be able to show its sums. The government’s strongest point is the mirror image: firm, low-carbon power has a value the tables understate, Koeberg delivers some of Eskom’s cheapest electricity, and letting coal stations retire in 2029 and 2030 without replacement means load shedding returns. The risk is delivery, not technology; and the Western record is the evidence the minister must answer before June 2027.
The second shock: a grid built for coal, a market built for sun
Whatever Pretoria decides, it must first rebuild the wires. The transmission plan calls for about 14,500 kilometres of new lines over a decade at R400 billion, the largest infrastructure project since 1994, yet Eskom built only 200 kilometres a year in recent years. The coal fleet is retiring: Hendrina, Camden and Grootvlei close around 2029 and 2030, and the winter outlook warns of a supply crunch without replacement capacity.
Inside the programme, Eskom’s minister has acknowledged the utility knows how to run a nuclear station, not build one; construction expertise must be bought or borrowed. The Nuclear Industrialisation Plan looks further, to small modular reactors and possibly reviving the Pebble Bed Modular Reactor, shelved in 2010 after R10 billion invested. The site choice will decide a local fight: Duynefontein is most advanced, Thyspunt most contested, its Alliance insisting nothing is approved.
What happens between now and June 2027?
Three dates matter now. The first is the end of November, when Ramokgopa has said he will publish a science-based case for the new reactors; the document on which the debate will turn, and the first chance to see the cost question answered with numbers. The second is 60 days of public comment, in which critics, industry and Thyspunt will file their cases. The third is June 2027, when the minister intends to publish the section 34 determination that would open procurement, with the regulator’s and the finance minister’s concurrence.
To watch: the details of Eskom’s feasibility study, still unpublished; the vendor and funding model, still undecided; and the court challenge the minister expects. If the position paper arrives with costs attached, the debate changes; and so does the story. Our answers page explains how the Bureau reads energy numbers; the next edition follows when the paper lands.
What we agree on, and what remains open
Established
- On the plan; South Africa will build 5,200 MW of new nuclear capacity by 2039 under IRP 2025, with the first 1,200 MW due by 2036 and an option to reach 10,000 MW.
- Eskom has submitted its feasibility study and the minister aims to publish the procurement determination before June 2027.
Contested
- On the numbers; new nuclear power is the most expensive new-build generation in Lazard’s latest cost study at $175–$255 per megawatt-hour, against $40–$98 for utility-scale solar and $37–$99 for onshore wind.
- The Western record is one of overruns, from Vogtle’s $36.8 billion to Flamanville’s €13.2 billion.
Still open
- What the 5,200 MW programme will actually cost; the only figure in public is an early estimate of about R250 billion.
- Nor which vendor, which site, or which funding model will be chosen, or whether the courts will let the determination stand.
What to watch
Questions, answered
Under the Integrated Resource Plan 2025, South Africa will build 5,200 MW of new nuclear capacity by 2039, with the first 1,200 MW due by 2036 and an option to expand to 10,000 MW. Eskom has submitted its feasibility study, and the minister aims to publish the procurement determination before June 2027, after public consultation.
No official total cost has been published. The only figure in public is an early estimate of about R250 billion, roughly $15 billion. Lazard’s latest study puts new nuclear power at $175–$255 per megawatt-hour, against $40–$98 for solar and $37–$99 for wind; though that comparison excludes grid and firming costs.
Energy scholar Mark Swilling argues the government has never presented the cost of the build in public, and that the modelling behind the 5,200 MW figure does not justify it. Critics point to cheaper solar and wind, to the Western record of overruns at Vogtle and Flamanville, and to a grid that already pays billions for curtailed renewable power.
The government says nuclear provides firm, low-carbon baseload power for energy security, decarbonisation and industrial growth, and that Koeberg already delivers some of the cheapest electricity in Eskom’s fleet. It promises a science-based case by the end of November, public consultation, and a determination before June 2027.
The department will publish its position paper by the end of November 2026, followed by 60 days of public comment. The minister intends to publish the section 34 determination before June 2027, with the energy regulator’s and the finance minister’s concurrence; and he expects the process to be challenged in court.